Servicing And Maintenance Of Sestw Phase III Extension
Odour Treatment Plants

 
.
   
LOCATION Singapore
CLIENT Hydunai Engineering & Construction Co. Ltd/
Sewerage Department, Singapore Public Utilities Board
PROJECT VALUE S$2,432,570.00
DATE
1 November 2001 - 30 November 2003
PROJECT SCOPE

Servicing and Maintenance of all equipments related to the 3 odour treatment plants which includes :

4 nos. of Chemical Scrubber
12 nos. of carbon Adsorption Cuts
8 nos. of Main Extraction Fans
Chemical storage and Dosing system
Pumps and motor
Instruments
Electrical panels
UNIQUENESS OF
PROJECT
The plants are maintained and in good operating conditions with the servicing and maintenance of all equipments within the Odour Treatment Plants (OTP). Theses OTPs remove odorous air, primarily Hydrogen Sulphide, Mercaptans and Ammonia from the entire works.