Jurong Industrial Water Works - High Lift Sump Station
 
The project is for the supply, installation and comissioning of equipment to a new High Lift Pump House.
.
   
LOCATION Singapore
CLIENT Sewerage Department, Singapore / Khoon & Co. Pte Ltd
CONSULTANT Executive Decisions Inc & Partners / PB Merz and McLellan Pte Ltd
PROJECT VALUE S$ 3,136,480
DATE
27 April 1998 - 27 July 1999
PROJECT SCOPE
Supply, installation and commissioning of Electrical & Mechanical equipment in association with the construction of a new High Lift Pump House pumping industrial water to the Jurong Island about 9 Km away.

Equipment includes pumps, surge tanks, transformers, high tension switch gears, control panels, standby generator set, overhead crane, etc.
UNIQUENESS OF
PROJECT
This is part of the overall project to increase the capacity of the Jurong Industrial Water Works to meet the demand of the chemical industrial complex at Jurong Island.